Road reconstruction
Wabush, Newfoundland and Labrador
Federal contribution
$388,449
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 3, 2020
202120222023
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Wabush
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Dec 20, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2021
- Construction end3 months earlyforecast Mar 31, 2023