Central Saanich - Senanus Watermain

Central Saanich, British Columbia

completeDrinking WaterMRIF
Federal contribution
$370,119
Federal share22%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2007
20082009201020112012
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
District of Central Saanich
Construction start
Jul 10, 2007(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 22, 2007