Brentwood Bay Sewer
Central Saanich, British Columbia
Federal contribution
$3.2M
$3,169,767
Federal share40%
of $7.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2023
today
2023202420252026
BuiltForecast
Approved 11 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District Municipality of Central Saanich
- Construction start
- Mar 25, 2024(actual)
- Construction end
- Sep 30, 2026(forecast)