Central Saanich - Centennial Park Multi Use Sport Box

Central Saanich, British Columbia

completeRecreationCCRIS
Federal contribution
$823,500
Federal share30%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Oct 10, 2024(actual)
Construction end
Sep 2, 2025(actual)

Against the original forecast

  • Construction start5 months lateforecast May 20, 2024
  • Construction end2 months lateforecast Jul 1, 2025