Pemberton New Water Supply
Federal contribution
$177,750
Federal share33%
of $533.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2007
20082009
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Pemberton
- Construction start
- Sep 4, 2007(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 21, 2007
Also in Pemberton
- Pemberton - Water Treatment Plant$3.3M
- Pemberton - Valley Soccer Field and Amenity Building$1.7M
- Lilwat Nation- Lilwat Health & Healing Centre Renovation$1.2M
- Pemberton - Regional Multi-Modal Transportation Hub - Phase 1$742.7K
- Village of Pemberton to Lil'wat Nation Friendship Trail: Pemberton Farm Road East Connector$418.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17308 in the federal list. How to read these figures.