Village of Pemberton to Lil'wat Nation Friendship Trail: Pemberton Farm Road East Connector

Pemberton, British Columbia

completeActive TransportationATF
Federal contribution
$418,200
Federal share39%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2023
2023
Built

Approved 7 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Village of Pemberton
Construction start
Aug 1, 2023(actual)
Construction end
Nov 7, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast May 31, 2023
  • Construction end5 weeks lateforecast Sep 30, 2023

Also in Pemberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64304 in the federal list. How to read these figures.