Pemberton - Ayers Dike Upgrade
Federal contribution
$203,921
Federal share33%
of $611.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2014
2015
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Pemberton Valley Dyking District
- Construction start
- Jul 1, 2014(actual)
- Construction end
- Mar 31, 2015(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2014
Also in Pemberton
- Pemberton - Water Treatment Plant$3.3M
- Pemberton - Valley Soccer Field and Amenity Building$1.7M
- Lilwat Nation- Lilwat Health & Healing Centre Renovation$1.2M
- Pemberton - Regional Multi-Modal Transportation Hub - Phase 1$742.7K
- Village of Pemberton to Lil'wat Nation Friendship Trail: Pemberton Farm Road East Connector$418.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44876 in the federal list. How to read these figures.