Pemberton - Regional Multi-Modal Transportation Hub - Phase 1
Federal contribution
$742,688
Federal share40%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20222023202420252026
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Pemberton
- Construction start
- May 7, 2024(actual)
- Construction end
- Feb 13, 2026(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Mar 20, 2026