Back to projects

Laurentian Hills Asset Management

Deep River, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,793
Federal share33%

of $11.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Laurentian Hills
Construction start
Jun 15, 2008(actual)
Construction end
Oct 26, 2009(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 15, 2007
  • Construction end7 months lateforecast Mar 31, 2009