Upgrade HVAC System

Deep River, Ontario

completeVentilationCVRIS
Federal contribution
$664,000
Federal share80%

of $830.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022202320242025
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 1, 2023(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 30, 2023
  • Construction end4 months lateforecast Aug 31, 2024