Minor upgrades to the raw water intake & pumping and piping systems low lift pumping station
Federal contribution
$34,705
Federal share50%
of $69.4K total eligible cost; the rest comes from other partners.
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Deep River
- Construction start
- May 15, 2017(actual)
- Construction end
- Jul 30, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 15, 2017
- Construction end4 weeks lateforecast Jun 30, 2017
Also in Deep River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51137 in the federal list. How to read these figures.