Minor upgrades to the raw water intake & pumping and piping systems low lift pumping station

Deep River, Ontario

completeDrinking WaterCWWF
Federal contribution
$34,705
Federal share50%

of $69.4K total eligible cost; the rest comes from other partners.

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Deep River
Construction start
May 15, 2017(actual)
Construction end
Jul 30, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 15, 2017
  • Construction end4 weeks lateforecast Jun 30, 2017