Parkdale Avenue sanitary sewer main replacement

Deep River, Ontario

completeWastewaterCWWF
Federal contribution
$81,432
Federal share50%

of $162.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Deep River
Construction start
Jan 1, 2018(actual)
Construction end
Aug 15, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Aug 1, 2017
  • Construction end14 months earlyforecast Sep 30, 2021

Also in Deep River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51133 in the federal list. How to read these figures.