Nakusp - Sewage Treatment Plant Upgrade
Federal contribution
$323,690
Federal share33%
of $971.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2007
200820092010
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Nakusp
- Construction start
- Jul 10, 2007(actual)
- Construction end
- Mar 31, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 22, 2007
- Construction end2 years earlyforecast Mar 31, 2012
Also in Nakusp
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17526 in the federal list. How to read these figures.