Nakusp and Area Bike Society - Mt. Abriel Recreation Site Phase 2.2 & 3
Federal contribution
$226,573
Federal share40%
of $566.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Nakusp and Area Bike Society
- Construction start
- May 3, 2020(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction end7 months lateforecast Dec 1, 2021
Also in Nakusp
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56234 in the federal list. How to read these figures.