Pressure Reducing Station and Supply Mains for Sleepy Hollow
Federal contribution
$86,650
Federal share33%
of $259.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2015
2016
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Nakusp
- Construction start
- Oct 1, 2015(actual)
- Construction end
- Apr 15, 2016(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2015
- Construction end5 months lateforecast Nov 15, 2015
Also in Nakusp
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46153 in the federal list. How to read these figures.