Comox Traffic Circle
Federal contribution
$566,596
Federal share29%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 9, 2007
20082009
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Comox
- Construction start
- Sep 4, 2007(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 21, 2007
- Construction end12 months earlyforecast Mar 31, 2010
Also in Comox
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17623 in the federal list. How to read these figures.