Guthrie Road Bicycle Lane Extensions
Federal contribution
$24,675
Federal share25%
of $98.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Comox
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Aug 28, 2009(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2009
- Construction end7 months earlyforecast Mar 31, 2010
Also in Comox
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29587 in the federal list. How to read these figures.