K’ómoks First Nation - Community Complex Upgrades and Food Security Storage Addition

Comox, British Columbia

completeVentilationCVRIS
Federal contribution
$718,555
Federal share100%

of $718.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
K’ómoks First Nation
Construction start
Jan 9, 2023(actual)
Construction end
Jul 31, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Nov 21, 2022
  • Construction end5 months earlyforecast Dec 31, 2023

Also in Comox

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60555 in the federal list. How to read these figures.