Back to projects

Asset Management

Nipissing, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,845
Federal share33%

of $11.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 4, 2007
20072008
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Nipissing
Construction start
May 4, 2007(actual)
Construction end
Feb 12, 2008(actual)

Against the original forecast

  • Construction end14 months earlyforecast Mar 31, 2009

Also in Nipissing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17653 in the federal list. How to read these figures.