Duncan - Dogwood Ridge Water System Improvements

Duncan, British Columbia

completeDrinking WaterMRIF
Federal contribution
$133,333
Federal share33%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 8, 2008
20082009201020112012
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 12, 2007(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 19, 2007

Also in Duncan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17679 in the federal list. How to read these figures.