North Cowichan & Duncan Dikes and Pump Station - Phase 3

Duncan, British Columbia

completeDisaster MitigationCC
Federal contribution
$2.2M
$2,231,034
Federal share33%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2014
201520162017
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
District of North Cowichan
Construction start
Mar 1, 2016(actual)
Construction end
Mar 31, 2017(actual)

Against the original forecast

  • Construction start10 months lateforecast May 1, 2015
  • Construction end12 months lateforecast Mar 31, 2016

Also in Duncan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44893 in the federal list. How to read these figures.