North Cowichan - Joint Utility Board Wastewater Treatment Plant Flood Protection Upgrade

Duncan, British Columbia

completeDisaster MitigationCC
Federal contribution
$1.3M
$1,282,634
Federal share31%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2010
20112012
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
District of North Cowichan
Construction start
Oct 18, 2010(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction end13 months lateforecast Feb 25, 2011