Duncan - Cowichan Valley Flood Protection (Phase 1)

Duncan, British Columbia

completeDisaster MitigationCC
Federal contribution
$2.6M
$2,583,332
Federal share33%

of $7.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2012
201220132014
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Oct 3, 2012(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jan 1, 2013