Back to projects

Opasatika Asset Management

Opasatika, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,483
Federal share33%

of $10.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Opasatika
Construction start
Jun 30, 2007(actual)
Construction end
Apr 6, 2009(actual)

Also in Opasatika