Upgrade Supervisory Control and Data Acquisition (SCADA) & Programmable Logic Controller (PLC) at Water Treatment Plant
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Opasatika
- Construction start
- Feb 8, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction end6 weeks lateforecast Nov 17, 2023
Also in Opasatika
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58918 in the federal list. How to read these figures.