Back to projects

Upgrade Supervisory Control and Data Acquisition (SCADA) & Programmable Logic Controller (PLC) at Water Treatment Plant

Opasatika, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Opasatika
Construction start
Feb 8, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Nov 17, 2023

Also in Opasatika