Repair and replace five curb valves to improve the water distribution system
Federal contribution
$7,740
Federal share48%
of $16.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Opasatika
- Construction start
- Jun 6, 2017(actual)
- Construction end
- Sep 15, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 1, 2017
- Construction end2 weeks earlyforecast Sep 30, 2018
Also in Opasatika
- Upgrade Supervisory Control and Data Acquisition (SCADA) & Programmable Logic Controller (PLC) at Water Treatment Plant$80.0K
- Opasatika Community Hub Renovation$52.9K
- Repair 7 hydrants in township to improve water distribution system effectiveness$14.0K
- Optimize green sand filter and diffusers$10.0K
- Repair main sewage pump house building$8.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48530 in the federal list. How to read these figures.