Back to projects

Repair and replace five curb valves to improve the water distribution system

Opasatika, Ontario

completeDrinking WaterCWWF
Federal contribution
$7,740
Federal share48%

of $16.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Opasatika
Construction start
Jun 6, 2017(actual)
Construction end
Sep 15, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 1, 2017
  • Construction end2 weeks earlyforecast Sep 30, 2018

Also in Opasatika