Optimize green sand filter and diffusers
Federal contribution
$10,000
Federal share50%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Opasatika
- Construction start
- Jul 23, 2018(actual)
- Construction end
- Aug 10, 2018(actual)
Against the original forecast
- Construction start18 months lateforecast Feb 1, 2017
- Construction end3 months earlyforecast Oct 31, 2018
Also in Opasatika
- Upgrade Supervisory Control and Data Acquisition (SCADA) & Programmable Logic Controller (PLC) at Water Treatment Plant$80.0K
- Opasatika Community Hub Renovation$52.9K
- Repair 7 hydrants in township to improve water distribution system effectiveness$14.0K
- Repair main sewage pump house building$8.9K
- Repair and replace five curb valves to improve the water distribution system$7.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48528 in the federal list. How to read these figures.