Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of North Glengarry
Construction start
Jun 18, 2007(actual)
Construction end
Sep 17, 2008(actual)

Against the original forecast

  • Construction end5 months earlyforecast Feb 28, 2009