Township of Dawson Asset Management

Rainy River, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,125
Federal share33%

of $9.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
2007200820092010
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Dawson
Construction start
Jun 18, 2007(actual)
Construction end
Oct 18, 2010(actual)

Against the original forecast

  • Construction end7 months lateforecast Mar 31, 2010

Also in Rainy River