Rehabilitation of Atwood Ave. Water and Waste Water Lines
Federal contribution
$652,259
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Rainy River
- Construction start
- May 25, 2010(actual)
- Construction end
- Nov 2, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jul 5, 2010
- Construction end5 weeks lateforecast Sep 30, 2010
Also in Rainy River
- Highway 11, Replacement of the Rainy River-Baudette International Bridge at Canada/United States Border$13.1M
- Third Street Water Distribution Upgrades$2.0M
- Rainy River Health Centre(Eldcap) HVAC & Sprinkler$1.2M
- Second Street and Broadway Avenue Rehabilitation$1.1M
- Water Line and Sanitary Sewer Line Replacement - 100-500 Atwood Avenue serving 20 residential and commercial buildings$151.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23089 in the federal list. How to read these figures.