Rainy River Health Centre(Eldcap) HVAC & Sprinkler
Federal contribution
$1.2M
$1,182,052
Federal share80%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
2022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Riverside Health Care Facilities Inc.- Rainy River Health Centre
- Construction start
- Mar 1, 2022(actual)
- Construction end
- May 1, 2025(actual)
Against the original forecast
- Construction start10 months lateforecast May 3, 2021
- Construction end4 months lateforecast Dec 31, 2024
Also in Rainy River
- Highway 11, Replacement of the Rainy River-Baudette International Bridge at Canada/United States Border$13.1M
- Third Street Water Distribution Upgrades$2.0M
- Second Street and Broadway Avenue Rehabilitation$1.1M
- Rehabilitation of Atwood Ave. Water and Waste Water Lines$652.3K
- Water Line and Sanitary Sewer Line Replacement - 100-500 Atwood Avenue serving 20 residential and commercial buildings$151.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59641 in the federal list. How to read these figures.