Back to projects

Water Line and Sanitary Sewer Line Replacement - 100-500 Atwood Avenue serving 20 residential and commercial buildings

Rainy River, Ontario

completeDrinking WaterCWWF
Federal contribution
$151,580
Federal share38%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Rainy River
Construction start
Sep 17, 2018(actual)
Construction end
Nov 17, 2018(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Jul 15, 2016
  • Construction end13 months lateforecast Oct 15, 2017

Also in Rainy River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48569 in the federal list. How to read these figures.