Replacement of street water main under Principale Street.
Federal contribution
$278,537
Federal share33%
of $835.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2008
20082009
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Batiscan
- Construction start
- Aug 1, 2008(actual)
- Construction end
- Dec 31, 2008(actual)
Also in Batiscan
- Program for the renewal of drinking water and wastewater pipes$398.0K
- Program for the renewal of drinking water and wastewater pipes$341.6K
- Program for the renewal of drinking water and wastewater pipes$139.1K
- Program for the renewal of drinking water and wastewater pipes$55.3K
- Reconstruction of P-1 well$48.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17856 in the federal list. How to read these figures.