Program for the renewal of drinking water and wastewater pipes
Federal contribution
$139,095
Federal share31%
of $448.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
20102011
Built
Approved 13 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Batiscan
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
Also in Batiscan
- Program for the renewal of drinking water and wastewater pipes$398.0K
- Program for the renewal of drinking water and wastewater pipes$341.6K
- Replacement of street water main under Principale Street.$278.5K
- Program for the renewal of drinking water and wastewater pipes$55.3K
- Reconstruction of P-1 well$48.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40610 in the federal list. How to read these figures.