Program for the renewal of drinking water and wastewater pipes
Federal contribution
$55,313
Federal share31%
of $178.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
20102011
Built
Approved 6 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Batiscan
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Batiscan
- Program for the renewal of drinking water and wastewater pipes$398.0K
- Program for the renewal of drinking water and wastewater pipes$341.6K
- Replacement of street water main under Principale Street.$278.5K
- Program for the renewal of drinking water and wastewater pipes$139.1K
- Reconstruction of P-1 well$48.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41688 in the federal list. How to read these figures.