Town of Mississippi Mills-Asset Management
Federal contribution
$5,103
Federal share33%
of $15.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Mississippi Mills
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Mar 23, 2009(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2008
Also in Almonte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17869 in the federal list. How to read these figures.