Renovations to Almonte Community Centre
Federal contribution
$651,740
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Mississippi Mills
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Also in Almonte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27605 in the federal list. How to read these figures.