Construction of a Mechanical Sewage Treatment Plant and Upgrade of Pump Station
Federal contribution
$9.1M
$9,103,809
Federal share33%
of $27.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Mississippi Mills
- Construction start
- Jun 9, 2010(actual)
- Construction end
- Nov 4, 2013(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2010
- Construction end16 months lateforecast Jun 30, 2012
Also in Almonte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24572 in the federal list. How to read these figures.