Township of Coleman Asset Management
Federal contribution
$1,555
Federal share33%
of $4.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 7, 2007
200720082009
Built
Approved 5 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Coleman
- Construction start
- May 15, 2007(actual)
- Construction end
- Dec 31, 2008(actual)
Also in Coleman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17878 in the federal list. How to read these figures.