Back to projects

Township of Coleman Asset Management

Coleman, Ontario

completeCapacity BuildingMRIF
Federal contribution
$1,555
Federal share33%

of $4.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 7, 2007
200720082009
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Coleman
Construction start
May 15, 2007(actual)
Construction end
Dec 31, 2008(actual)

Also in Coleman

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17878 in the federal list. How to read these figures.