Replacement of Water Distribution System

Coleman, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$1.8M
$1,810,901
Federal share45%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Coleman
Construction start
Jun 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 31, 2010

Also in Coleman

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27366 in the federal list. How to read these figures.