Bass Lake Park Upgrades
Federal contribution
$79,998
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
today
202220232024202520262027
BuiltForecast
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Coleman
- Construction start
- Sep 20, 2023(actual)
- Construction end
- Dec 31, 2026(forecast)
Against the original forecast
- Construction start13 months lateforecast Aug 31, 2022
Also in Coleman