Water System Upgrade - Phase 4
Port au Port East, Newfoundland and Labrador
Federal contribution
$56,816
Federal share27%
of $213.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.8 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Port Au Port East
- Construction start
- Jun 23, 2009(actual)
- Construction end
- Aug 12, 2009(actual)
Against the original forecast
- Construction end4 months earlyforecast Nov 30, 2009
Also in Port au Port East
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17954 in the federal list. How to read these figures.