Watermain Replacement
Port au Port East, Newfoundland and Labrador
Federal contribution
$404,561
Federal share49%
of $829.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Port au Port East
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Aug 18, 2017(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Aug 1, 2017
- Construction end2 weeks earlyforecast Sep 4, 2017
Also in Port au Port East
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47077 in the federal list. How to read these figures.