Waterline Replacement - Romaines Road

Port au Port East, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$262,472
Federal share40%

of $656.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
2021
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port au Port East
Construction start
Jul 12, 2021(actual)
Construction end
Aug 20, 2021(actual)

Against the original forecast

  • Construction end3 months earlyforecast Nov 30, 2021

Also in Port au Port East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56780 in the federal list. How to read these figures.