Town of Whitby - Asset Management
Federal contribution
$16,261
Federal share33%
of $48.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008200920102011
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Whitby
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Nov 19, 2010(actual)
Against the original forecast
- Construction end2.4 years lateforecast Jun 15, 2008
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Waterfront Trail Redevelopment for Whitby, Ontario$2.6M
- Wireless Infrastructure Upgrade Project Group$2.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18008 in the federal list. How to read these figures.