City of Cornwall Asset Management

Cornwall, Ontario

completeCapacity BuildingMRIF
Federal contribution
$16,830
Federal share33%

of $50.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
20072008
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Cornwall
Construction start
Jun 1, 2007(actual)
Construction end
Sep 22, 2008(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2009

Also in Cornwall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18049 in the federal list. How to read these figures.