Township of Machar Asset Management
Federal contribution
$3,637
Federal share33%
of $10.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 27, 2007
2007200820092010
Built
Approved 7 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Machar
- Construction start
- Jun 27, 2007(actual)
- Construction end
- Jun 14, 2010(actual)
Against the original forecast
- Construction end14 months lateforecast Mar 31, 2009
Also in South River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18072 in the federal list. How to read these figures.