Township of Hamilton Asset Mangement
Federal contribution
$4,976
Federal share33%
of $14.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 7, 2007
20072008
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Hamilton
- Construction start
- Jun 15, 2007(actual)
- Construction end
- Feb 7, 2008(actual)
Against the original forecast
- Construction end4 months earlyforecast Jun 15, 2008
Also in Hamilton