Asset Management Program

Owen Sound, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,882
Federal share33%

of $14.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Georgian Bluffs
Construction start
Jun 1, 2007(actual)
Construction end
Jan 26, 2009(actual)

Against the original forecast

  • Construction end4 months lateforecast Sep 15, 2008