Back to projects

Lake of the Woods Asset Management Program

Rainy River, Ontario

completeCapacity BuildingMRIF
Federal contribution
$2,997
Federal share33%

of $9.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 4, 2007
2007200820092010
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 4, 2007(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Rainy River